What Are the Different Types of Task Dependencies in Microsoft Project?

Microsoft Project is a project management tool that helps teams to manage tasks, track progress, allocate resources, and set dependencies between tasks. One of the key features of Microsoft Project is its ability to set different types of task dependencies. Task dependencies are links between tasks that determine the order in which they should be completed. In this article, we will discuss the different types of task dependencies in Microsoft Project and how they can be used to manage projects effectively.

Finish-to-Start (FS) Dependency

The most common type of task dependency is the Finish-to-Start (FS) dependency. This means that one task (the successor task) cannot start until another task (the predecessor task) has finished. FS dependencies are often used when one task is dependent on the output of another task. For example, you cannot start building a house until the foundation has been laid.

Here is an example of a Finish-to-Start dependency:

Predecessor Task Successor Task
A B

In this example, Task B (the successor task) cannot start until Task A (the predecessor task) has finished.

Start-to-Start (SS) Dependency

A Start-to-Start (SS) dependency means that one task cannot start until another task has started. This type of dependency is often used when there is a relationship between the start dates of two tasks. SS dependencies are less common than FS dependencies, but they can be useful in some situations.

Here is an example of a Start-to-Start dependency:

Predecessor Task Successor Task
A B

In this example, Task B (the successor task) cannot start until Task A (the predecessor task) has started.

Finish-to-Finish (FF) Dependency

A Finish-to-Finish (FF) dependency means that one task cannot finish until another task has finished. This type of dependency is often used when there is a relationship between the end dates of two tasks. FF dependencies are less common than FS dependencies, but they can be useful in some situations.

Here is an example of a Finish-to-Finish dependency:

Predecessor Task Successor Task
A B

In this example, Task B (the successor task) cannot finish until Task A (the predecessor task) has finished.

Start-to-Finish (SF) Dependency

A Start-to-Finish (SF) dependency means that one task cannot finish until another task has started. This type of dependency is the least common and is used infrequently. SF dependencies are often used when there is a negative relationship between tasks or when tasks need to overlap.

Here is an example of a Start-to-Finish dependency:

Predecessor Task Successor Task
A B

In this example, Task B (the successor task) cannot finish until Task A (the predecessor task) has started.

Best Practices for Setting Task Dependencies

When setting task dependencies in Microsoft Project or any project management tool, it is important to follow best practices to ensure that your project plan is accurate and realistic. Here are some best practices for setting task dependencies:

  • Identify all the dependencies between tasks before you start setting them up.
  • Use the appropriate type of dependency for each relationship.
  • Avoid circular dependencies, where two or more tasks depend on each other.
  • Be careful when using SF dependencies, as they can be confusing and difficult to manage.
  • Continuously monitor and update the task dependencies as the project progresses.

Conclusion

Task dependencies are an essential aspect of project management, and Microsoft Project provides a range of options for setting them up. Choosing the right type of dependency for each relationship is crucial to the success of your project plan. By following best practices and continuously monitoring and updating the dependencies, you can ensure that your project stays on track and meets its objectives.

0%